July 24

The construction work has got on to a strong start from 3rd June 2024. The leaky east end extension is demolished and being rebuilt with the underground drainage relayed, hall floor protected and the external battening started and a bat loft built above the changing rooms. The broad programme for Culmex continues as follows: 11 Jun […]

Meet the Stage 4 Design Team (Not actual photo!)

Lead by Chartered Architect: Lewis Barton, Barton Architects. Mechanical and Electrical Engineer: Chris Ayres, Pivotal. Quantity Surveyor: Steve Wickes, Jemmy QS. Structural Engineer: Mark Hartis, structureHaus. Ecology Consultant: Chris Turner, Lakeway Ecological.

Open Day Held

The design team at the village hall ran a community engagement open day to get feedback from the village and surrounding areas on the plans for the hall.